How to Design Classrooms for Optimal Acoustics

How to Design Classrooms for Optimal Acoustics

By Marcus Chen ·

1) Project overview: what, where, who, and why

In spring 2025, SonusGearFlow was brought in as the acoustics and AV integration partner for a classroom refresh at East Ridge Community College in Madison, Wisconsin. The scope covered eight general-purpose classrooms in the Humanities building: six “standard” rooms (approximately 8.5 m x 10.5 m with 3.0 m ceilings, ~270 m3) and two larger active-learning rooms (approximately 12 m x 14 m with 3.4 m ceilings, ~570 m3).

The client team included Facilities (owner’s rep), the campus AV manager, and an architectural firm already under contract for new finishes and lighting. Our role was to design and document an acoustic treatment package that would improve speech intelligibility for instructors and hybrid learning, while staying inside a fixed construction window (10 weeks, summer break) and a capped budget of $180,000 for all eight rooms (materials, labor, commissioning).

The “why” was measurable, not aspirational. Student accessibility requests had increased, instructors reported vocal fatigue, and the hybrid capture system installed during 2021 was underperforming: remote participants complained of “echoey” audio and “muffled questions,” even when microphone gain was increased. The campus AV manager also wanted a repeatable recipe that could be used later in other buildings.

2) Challenges and requirements at the outset

The initial walk-through showed the classic classroom acoustics failure mode: hard parallel boundaries, low absorption, and multiple noise sources. Each standard classroom had painted CMU sidewalls, a gypsum board front wall, a glass sidelighted corridor wall, and an ACT ceiling with older, low-NRC tiles. Floors were sealed concrete or VCT. Furniture had changed from rows to pods, which increased student-to-student cross talk and raised the noise floor.

The baseline measurements confirmed the subjective complaints. In two representative rooms we measured:

Requirements were established with the owner and AV team:

The biggest constraint was schedule. The building was occupied until May 20, and classes resumed August 1. That left roughly 10 weeks for design finalization, procurement, installation, and commissioning—with predictable procurement risk for acoustic materials.

3) Approach and methodology chosen

We treated this as an acoustic + electroacoustic system problem rather than “add panels until it sounds better.” The methodology combined field measurements, acoustic modeling, and coordination with mechanical and architectural trades.

Workflow in brief:

  1. Capture baseline metrics (T60 by band, STI mapping, background noise spectra) and document noise sources.
  2. Model each room type in EASE to estimate required absorption area for target T60 and to validate loudspeaker coverage.
  3. Prioritize interventions that reduce both reverberation and noise: ceiling NRC upgrades, targeted wall absorption, and HVAC diffuser changes.
  4. Integrate the acoustic plan with the existing AV: ceiling speakers, DSP AEC, and microphone placement.
  5. Commission: verify T60, STI, and noise criteria; tune DSP with real-room acoustic data after treatment installation.

The team used a calibrated measurement chain: Earthworks M30 measurement mic, Focusrite Scarlett interface, and Room EQ Wizard for T60 and RT by octave band; NTi XL2 for spot-check SPL and NC curves; and a controlled speech source for STI mapping. The AV platform used Biamp TesiraFORTÉ for AEC and routing in each room; we planned to keep that and improve the room conditions so the DSP would work less aggressively.

4) Step-by-step execution narrative

Week 1–2: Baseline testing and stakeholder alignment

We measured two standard rooms and one active-learning room in detail, then used the results to set design targets for all eight. We also recorded 15-minute HVAC noise samples during occupied-mode airflow. The mechanical contractor confirmed the VAV boxes were operating at higher-than-design minimums due to a previous balancing workaround.

A key early decision was to define “teaching mode” HVAC settings. Facilities agreed to a new schedule profile: reduce minimum airflow during instruction while maintaining ventilation rates via extended pre-occupancy purge. That shifted the problem from “fix everything in sheet metal” to “optimize controls and address obvious noise generators.”

Week 3–4: Acoustic design and procurement

Modeling showed we needed roughly 45–55 m2 of additional equivalent absorption area (A) per standard room to reach 0.60 s T60, assuming an average occupancy of 24 students. The existing ACT ceiling tile tested closer to NRC 0.55.

We specified a two-part treatment strategy:

For the active-learning rooms, the model indicated that ceiling treatment alone would not control lateral flutter between large glass areas and CMU. We added upper-wall absorption and limited diffusion to preserve “liveliness” without sacrificing intelligibility.

Procurement was timed aggressively. We issued submittals in week 3, approved in week 4, and pre-ordered ceiling tiles and panel hardware. Lead times were 4–6 weeks for the panels and 2–3 weeks for ceiling tiles. To reduce risk, we used a single panel line across all rooms and standardized sizes (600 mm x 1200 mm and 600 mm x 600 mm).

Week 5–7: Installation coordination with trades

Installation sequencing mattered. Ceiling work had to precede lighting trim and projector alignment. We coordinated a mock-up in one standard room: ceiling tile replacement, then panel placement, then AV tuning. The mock-up validated that the projector brightness and screen reflections were unaffected and that wall panels didn’t conflict with whiteboards.

The HVAC contractor swapped high-velocity diffusers for perforated-face diffusers in four rooms where measurements showed turbulent noise. Two VAV boxes received internal liner replacement and damper adjustment. Not every mechanical fix was possible in the schedule, so we focused on interventions with predictable results.

Week 8–10: Commissioning, DSP tuning, and documentation

After the acoustic materials were installed, we re-measured T60 and ran STI maps at three listening positions per room (front third, middle, rear). We then revisited the Biamp DSP configuration. In the pre-upgrade state, AEC was fighting late reflections and noise, so the integrator had used higher noise reduction and more aggressive gating. Post-upgrade, we reduced noise reduction depth by 3–6 dB, relaxed gate thresholds, and lowered overall gain structure by ~2 dB to improve naturalness while maintaining far-end clarity.

Documentation included as-built panel layout drawings, product data sheets, measurement reports (before/after), and a repeatable checklist for future classroom refreshes.

5) Technical decisions and trade-offs made

Several decisions were trade-offs between ideal acoustics and real-world constraints:

6) Results and outcomes with specific details

The post-install measurements showed consistent improvement across all eight classrooms.

On the hybrid learning side, remote participants reported fewer “roomy” artifacts and better pickup of student questions. Objectively, we saw a reduction in AEC tail length requirements and fewer instances of double-talk suppression triggering during group work. The AV manager also noted that instructors stopped increasing mic gain mid-class—an informal but meaningful indicator that the room was no longer fighting speech.

Budget and schedule performance was also trackable. Total spend landed at $172,400: $86,000 in ceiling tile materials and labor, $58,500 in wall panels and labor, $15,400 in HVAC adjustments and diffuser replacements, and $12,500 in measurement, commissioning, and documentation. The work completed in 9.5 weeks, leaving a few days of buffer before faculty returned.

7) Lessons learned and what could be done differently

Three lessons stood out.

First, the mock-up room prevented costly rework. It revealed that a proposed panel location conflicted with a door swing and that one lighting row created glare on a new whiteboard. Fixing those on paper saved a day of labor in every room.

Second, HVAC noise should be treated as a core acoustic variable, not a separate discipline. Even after improving reverberation, NC-38 in one classroom still masked consonants for soft-spoken instructors. If we had more time, we would have specified quieter terminal units in that branch and added duct attenuation rather than relying on control changes alone.

Third, panel durability details matter in schools. In one room, the first installed panel fabric was too light in color and showed scuffs from chair contact during summer workshops. We switched to a darker, heathered fabric with a higher abrasion rating for the remaining rooms. If we were starting over, we would select the final fabric from an on-site abuse test (chairs, bags, cleaning chemicals) rather than a spec sheet.

8) Takeaways applicable to other projects

Designing classrooms for optimal acoustics is not a single product choice—it’s a sequence of decisions across architecture, mechanical noise control, and electroacoustic behavior. The East Ridge project was successful because the team treated intelligibility as the deliverable, measured it, and verified it under realistic operating conditions. For audio engineers and project managers, the repeatable pattern is straightforward: define targets, model and measure, spend money where it affects speech the most, and commission the room as a complete system.