How to Achieve ASTM E90 Certification

How to Achieve ASTM E90 Certification

By James Hartley ·

1) Project overview: what, where, who, and why

In late 2024, Sonus Gear Flow was asked to document and support a sound isolation verification program for a tenant-improvement project inside a mixed-use building in Somerville, Massachusetts. The client was a boutique post-production studio called Northline Edit, moving into a 3,800 sq ft second-floor suite above a ground-floor café and adjacent to a co-working space. Their lease required formal third-party test documentation demonstrating that their two critical rooms—the mix room and the VO booth—met an airborne sound isolation target equivalent to STC 60 for the demising wall and STC 55 for the corridor wall.

Because the studio planned to market the rooms to outside clients, they wanted the validation to be more than “we built it like an STC 60 wall.” They specifically requested testing aligned with ASTM E90 (Standard Test Method for Laboratory Measurement of Airborne Sound Transmission Loss of Building Partitions and Elements). The twist: the project wasn’t in a laboratory. We addressed this by executing a field test program using ASTM E336 for in-situ measurements, while designing and documenting the construction to match an ASTM E90 laboratory-rated assembly. The deliverable was a certification package commonly requested by landlords and insurers: (1) assembly documentation referencing E90 lab data from a recognized lab report, plus (2) on-site verification data demonstrating the installed construction met the isolation objective when measured in the field.

The core team included Northline’s project manager, the GC (a small commercial contractor), the architect, a mechanical subcontractor, and Sonus Gear Flow providing acoustic consulting and test coordination. Third-party measurements were performed by an independent acoustical test agency using calibrated instrumentation and traceable records.

2) Challenges and requirements at the outset

Three constraints defined the project before a single stud was ordered:

The performance requirement was not stated as “transmission loss at each third-octave band,” but as an STC target. For certification purposes, we needed to show the installed wall behaved consistently with an assembly that has recognized lab-tested performance per ASTM E90. The project manager also wanted a predictable path to pass/fail without expensive rework, so we baked measurement checkpoints into the schedule.

3) Approach and methodology chosen

We used a two-pronged method:

  1. Design to a known ASTM E90-tested assembly: We selected a demising partition configuration with a published E90 lab report indicating STC 60+ under controlled conditions, then documented the build in a way that could be compared line-by-line to that lab assembly (stud gauge, spacing, insulation density, gypsum type and thickness, screw patterns, sealant, and penetrations).
  2. Verify the installation with ASTM E336 field testing: Field conditions rarely match the lab. So we planned a test after drywall, sealing, and doors were installed but before final finishes locked us out of access. We targeted field results consistent with FSTC 55–58 for the demising wall, understanding that field numbers often come in 3–10 points below lab STC because of flanking and workmanship variability.

For equipment, the test agency specified a dodecahedron source capable of high output and predictable directivity, a measurement mic with recent calibration, and analysis software supporting third-octave band processing and STC calculation. They used a NTi Audio DS3 dodecahedron speaker driven by an NTi PA3 power amplifier, and measurement via an NTi XL2 analyzer with a Class 1 mic. Sound level checks were cross-verified with a Brüel & Kjær 2250 brought by the agency lead for redundancy.

4) Step-by-step execution narrative

Week 1–2: Preconstruction documentation and risk mapping

We started with a 90-minute kickoff onsite. Instead of discussing “STC walls” in general, we walked the perimeter of the planned mix room and identified every likely flanking path: slab edge, beam pockets, façade mullions, existing pipe penetrations, and the shared plenum above the corridor. We then produced a one-page “isolation risk map” for the GC. This became the reference during framing and MEP rough-in.

We also issued a submittal package listing acceptable equivalent materials. The owner preferred a specific gypsum brand for supply reasons, so we pre-approved alternates that matched density and Type X requirements. This prevented last-minute substitutions that can derail performance.

Week 3–5: Framing and decoupling details

The demising wall assembly was built as a double-stud wall with a 1 in air gap. Each stud line used 3-5/8 in 20 ga metal studs at 24 in o.c. on separate tracks. The key instruction to the framing crew was simple: no bridging between frames—no shared top track, no scraps used as “stiffeners,” and no electrical boxes spanning the cavity.

At the slab and underside of structure, we used a continuous bead of non-hardening acoustical sealant under tracks. The GC wanted to use standard construction adhesive at first, but we rejected it because it cures rigid and can create unintended mechanical coupling. We specified OSI SC-175 (or equivalent) for its long-term flexibility.

Week 6: Insulation and pre-drywall inspection

Insulation was 3-1/2 in mineral wool (nominal 2.5 lb/ft³) in each stud cavity. We didn’t overpack; we insisted on full depth without compression. Overstuffed batts can bow gypsum and create fastener gaps that leak sound.

Before drywall, we performed a “flashlight inspection” for air paths. With the lights off, a bright LED light was placed on one side of the wall while observers on the other side checked for light leaks at slab edges, track discontinuities, and around preinstalled sleeves. We found two problem zones: a 3/8 in gap at the beam web and a poorly cut sleeve around a condensate line. Both were sealed before board went up.

Week 7–8: Drywall layering, damping, and airtightness

For the demising wall, each side received two layers of 5/8 in Type X gypsum. The first layer was installed vertically with screws per manufacturer recommendations. The second layer was offset so seams did not align. Between layers, we used a constrained-layer damping compound at a controlled application rate—approximately 2 tubes per 4x8 sheet—to improve mid-band transmission loss. We documented batch numbers and coverage rates because “we used Green Glue” is not the same as proving consistent application.

At the perimeter of each layer, we left a 1/4 in gap to avoid hard contact to slab and columns, then filled it with acoustical sealant. The GC initially wanted to tape and mud the corners flush to the slab; we required the resilient gap remain and be sealed, not bridged with rigid compound.

Week 9: Doors, glazing, and penetrations

The corridor wall required STC 55-class performance, but the biggest failure point is almost always the door set. For the mix room entry, we selected a 1-3/4 in solid-core door, 20-minute rated, with full perimeter compression seals and an automatic drop seal. Hardware included a cam-lift hinge to improve consistent latch-side compression. We avoided dual doors due to space and egress constraints, but we did specify a heavier leaf (approx. 110 lb) and reinforced frame anchoring.

All electrical boxes in the demising wall were prohibited. For the corridor wall, any boxes were installed in surface raceway inside the room rather than recessed in the partition. HVAC penetrations were routed through lined flex with at least two bends and a lined plenum box to avoid a straight-line sound path.

Week 10: Pre-test commissioning and background noise management

Two days before the test, we conducted a quick internal check using a portable source and measurement mic—not to “predict STC,” but to identify gross leaks. We played pink noise at moderate level and walked the receiving side with a handheld SPL meter, listening for localized hiss indicative of air gaps. A consistent leak showed up at the door undercut where the drop seal hadn’t been adjusted. That adjustment alone typically changes real-world isolation more than adding another layer of drywall.

To ensure sufficient test dynamic range, we scheduled official testing from 6:30 a.m. to 9:30 a.m. before the café ramped up. The building’s base HVAC was kept on (as required by the standard for realistic conditions), but we temporarily disabled the studio’s internal supply fan during measurements to reduce receiving room noise floor.

5) Technical decisions and trade-offs made

6) Results and outcomes with specific details

Testing was performed in accordance with ASTM E336 procedures, with third-octave band measurements from 125 Hz to 4000 Hz, room averaging across multiple mic positions, and correction for background noise. The source room level was maintained high enough to achieve at least a 45 dB level difference above the receiving room noise floor in most bands.

Demising wall (mix room to co-working space): The final calculated result was FSTC 57. The measured transmission loss curve tracked the expected mid-band performance closely, with the largest weakness observed in the 125–160 Hz region—consistent with flanking through structure and the reality of field conditions.

Corridor wall and door (mix room to corridor): The wall alone tested stronger, but the assembled system including the door set produced FSTC 51 on the first pass, which did not meet the project’s practical expectation for privacy. The analysis pointed to door leakage rather than wall deficiency: strong high-frequency transmission and a signature consistent with perimeter gaps.

We paused final sign-off and executed corrective actions within 48 hours:

On the re-test, the corridor assembly improved to FSTC 54. While still below the lab-rated wall value, it achieved the client’s functional goal: intelligible speech from the corridor was reduced to a murmur, and typical session playback at 83 dB SPL (C-weighted) inside the mix room did not generate complaints during normal co-working hours.

Timeline-wise, the acoustic scope from kickoff to final field report took 11 weeks. The independent test agency delivered the stamped report within 5 business days of the final measurement session. The total cost attributable to acoustic detailing and testing (consulting time, documentation, and two field test visits) landed at roughly $14,800, excluding construction materials.

7) Lessons learned and what could be done differently

The project succeeded, but two items are worth calling out as “next time, do it earlier” improvements:

We also would have benefited from adding a small accelerometer-based check on suspected structural flanking points. While not required for certification, vibration measurements can help explain low-frequency anomalies and guide whether additional isolation (floating floor, isolated ceiling) is justified.

8) Takeaways applicable to other projects

For audio engineers and project managers, the core lesson is that certification-grade outcomes come from making sound isolation measurable and repeatable: pick an assembly with known lab performance, build it without “small” deviations, and verify the installed result with field-appropriate standards. When the inevitable gap or flanking path shows up, you’ll have the data and access needed to fix it quickly—and you’ll end up with documentation that holds up under landlord scrutiny and client expectations.