How to Measure and Improve Sound Transmission Class

How to Measure and Improve Sound Transmission Class

By Marcus Chen ·

1. Project overview: what, where, who, and why

In March, SonusGearFlow was brought into a tenant-improvement buildout for a post-production suite inside a mixed-use building in Culver City, California. The project was a 1,850 sq ft facility on the second floor: a picture editorial room, a VO booth, a small mix room (nearfield-focused), and a machine closet. The client was a boutique post house expanding from a single-room operation into a space that could handle concurrent sessions without schedule collisions.

The “why” was straightforward: the space sat above street-level retail and shared a demising wall with a Pilates studio. The post house had already signed a five-year lease. They needed predictable isolation to keep VO takes clean during daytime foot traffic and to avoid being the reason the adjacent tenant complained at night.

The team included the client’s project manager, a general contractor (GC) with commercial TI experience, an MEP engineer, and our role covering acoustic design, measurement, and construction verification. The client requested a measurable target tied to a standard metric they could explain to ownership and insurers. We aligned on Sound Transmission Class (STC) as the primary rating for airborne isolation, with a secondary emphasis on low-frequency performance and flanking control that STC alone does not fully capture.

2. Challenges and requirements at the outset

At kickoff, three constraints defined the project:

We translated these into measurable requirements:

3. Approach and methodology chosen

We used a three-part methodology:

  1. Measure the baseline: Before demolition, we ran quick field tests on the existing demising wall and a representative interior partition. This established realistic starting points and identified flanking paths.
  2. Design for STC with buildable assemblies: We specified wall assemblies with known lab STC ratings, then adjusted for field realities. For example, a lab-rated STC 63 wall might produce FSTC 55–60 depending on workmanship and flanking.
  3. Verify during construction: We scheduled two on-site “hold points”: (a) after framing and MEP rough-in but before gypsum, and (b) after first layer of gypsum before final sealing and second layer. This let us catch bridging, back-to-back boxes, unsealed edges, and ceiling plenum shortcuts while they were still cheap to fix.

For measurement, we used a calibrated field kit:

While STC is a single-number rating derived from transmission loss (TL) across 125 Hz to 4 kHz, we also logged the full 1/3-octave spectra and noted deficiencies below 125 Hz, because adjacent tenant bass-heavy music and footfall-induced structure-borne components were expected.

4. Step-by-step execution narrative

Week 1–2: Baseline testing and site investigation

We conducted baseline E336-style measurements between the future mix room area and the Pilates demising wall. With existing finishes in place, the measured FSTC was 36. The spectrum showed predictable weakness at 125–250 Hz, and we found two major leakage paths:

We also walked the slab/deck and noted that the Pilates studio had a hard floor and frequent impact activity. That would not be solved by STC upgrades alone, but airborne isolation still needed to be robust to reduce airborne music and instructor voice spill.

Week 2–3: Assembly selection and detailing

For the demising wall, we recommended a buildable, high-performing assembly without requiring a full room-within-room:

For interior partitions (mix room to editorial, editorial to VO), we used double-stud or staggered-stud assemblies depending on space:

Week 4–6: Rough framing verification (first hold point)

At framing, we inspected for mechanical bridging. Two issues came up that would have undermined the design if left alone:

We also coordinated with electrical to avoid back-to-back boxes. Where outlets were unavoidable on both sides of a partition, we required offset placement with at least one stud bay separation, putty pads on all boxes, and sealed conduit penetrations.

Week 6–8: First gypsum layer and interim checks (second hold point)

Once the first layer of gypsum went up, we performed an interim air-leak inspection rather than a full STC test. This is where many projects win or lose: a high-STC assembly can behave like a low-STC assembly if it leaks.

We used a simple but effective method: play broadband noise in one room and sweep the perimeter with a measurement mic and headphones, listening for “hot” points. We found leakage at:

All were corrected before the second layer, when access would be harder.

Week 8–10: Doors, ceiling, and flanking control

Doors were the next critical item. The client initially wanted standard commercial hollow-core doors. We pushed back with numbers: even a great wall is undermined by a weak door. We selected:

For the ceiling, the biggest flanking risk was the shared plenum. Over the most sensitive partitions, we specified that walls continue to the deck, and where that was impossible (around existing beams and MEP), we added gypsum “ceiling breaks” and sealed soffit returns to prevent sound from traveling over the top through open ceiling space.

HVAC was treated as both a noise source and a transmission path. We added lined duct sections (1" duct liner, 5–8 ft where space permitted), specified low-velocity grilles, and avoided straight “line of sight” return paths between rooms. Where a transfer path was unavoidable, we used lined transfer boots with two 90-degree turns to increase attenuation.

5. Technical decisions and trade-offs made

Several trade-offs shaped the final system:

6. Results and outcomes with specific details

Post-construction testing occurred in week 11, after doors, seals, and final paint, but before furniture fully loaded the rooms. We conducted ASTM E336-style tests with multiple mic positions and averaged levels to reduce spatial variance.

Measured results:

Operational outcomes after move-in:

7. Lessons learned and what could be done differently

8. Takeaways applicable to other projects

This project finished on time within the 11-week construction window, met the client’s isolation goals where it mattered most, and—equally important—left behind a repeatable process: baseline measurement, realistic field targets, buildable assemblies, and verification at the moments when fixes are still cheap.